Home

Road and Bridge Report: District 1 (June 2014)

PDFPrintE-mail

This week we are working to continue chipping in the Edgewater Park area, while also applying the second layer on Little Bear Loop. We hope to finish the area this week, weather permitting.

 

Road and Bridge Report: District 1 (May 2014 Part 2)

PDFPrintE-mail

Road work continues in District 1 this week, as crews continue priming Lakeside. Upon completion, work will begin on Glover Road and Little Bear Loop. The roads will be oily and sticky, so we are encouraging drivers to please proceed slowly for your own safety. 

Recycling is also expected to begin on Cache Road this week, weather permitting. It will be repaired withing two to four weeks, depending on the weather and strength of the base. 

 

Please pay attention to signs and crews in the roads. As always, thank you for your patience. 

 

Road and Bridge Report: District 3 (April 2014)

PDFPrintE-mail

Another month with little rainfall, however the grass is beginning to grow and we have started our mowing operations.

 The road crew has continued to prepare roads to be oil and chipped this summer. They have recycled the road surface on two miles of McClung Road between State Highway 59 and Shroyer Road.  This is the last of our FEMA funded roads. 

We have been working on funds to do a 2 inch overlay on the Meers-Porterhill Road which is classified as a major collector and did not qualify for FEMA funds.  The total cost of this project would be about one million dollars.

We also have Crater Creek Road between Coombs and Woodlawn Roads, Chattanooga’s Cemetery Road, and Paradise Valley Road north of Meers-Porterhill Road prepared and ready to oil & chip.

The crew will next move to Holsey Acres Road from Old Cache Road to Bandy Road and 2nd Street in the City of Cache.

H.K. Builders have started the bridge on Boulder Creek at Gore Blvd.  Construction is almost half completed. They should be finished by the first of July.

Several of our crew worked at the Fair Grounds hauling off woodchips that was used in the stock show.  Once the wood chips are used for such an event, it has so much manure and trash in it that it has to be hauled off.

Read more...

 
 

Road and Bridge Report: District 1 (May 2014)

PDFPrintE-mail

Road crews have plans this week, weather permitting, to oil and chip Tony Creek Road, from Wolf Road to Watts Road. The road will be closed for for a couple of days to allow the crews to safely work in the area. This closing could potentially begin as early as today or tomorrow. Please pay close attention to road signs in the area. 

 

Road and Bridge Report: District 1 (April 2014)

PDFPrintE-mail

The warm weather has allowed for District 1 road crews to get back out and continue improving county roads. Work began this month recycling the roads in the Lakeside area, then moving to Little Bear Loop. Both jobs were completed and will be chipped back by mid June.

Next up was the Edgewater area., which will begin this week. Prep work will be done Tuesday before the final chipping on Thursday. After Edgewater is completed, crews will shift focus to entry areas around Edgewater. 

Work on Cache Road will begin next week and can expect to be rechipped middle to late May, which should allow the base time to be fixed in trouble spots. 

Additional work is being done cleeaning out the bar ditch from 75th Street to 45th Street.

Lastly, construction on the bridge on Woodlawn will begin today. The contracts allows 120 days to complete the project, straighten the road and make the area safer. Once completed, the piece of road will be reopened.

 

Thank you for your patience while we work. Also, please pay close attention to the upcoming tax vote and elections. Be sure to educate yourselves on each item. More information on the county tax can be found on this website by clicking the link on the left side of the page. Thank you

 
 

Page 3 of 10