District 3: Road and Bridge Report

Don Hawthorne, County Commissioner

 

When the work is outside, weather is always a factor. Maybe that goes without saying, but it is the truth when it comes to county road work. This summer has been crazy, going from drought to hard and then soaking rains, putting mowing, grading, and construction behind.

T&G Construction was the low bidder and completed the 2” asphalt overlay of 8th Street in Cache from US 62 to Cache Road, and the 3” overlay of Indiahoma Road from US 62 to Show Place Avenue in Indiahoma. The County did the road preparation work and the Comanche Nation Department of Transportation (CNDOT) funded the overlay. Director Adrian Tehauno and his staff are great to work with, and fund projects that the County could not have afforded.

The CNDOT also funded the oil and chipping of Indiahoma Road from Coombs Road to Baseline Road. On this project the tribe paid for the materials and the County funded the road base work and putting down the materials.

We are currently working with the CNDOT to do a 2” asphalt overlay of four miles of Meers-Porter Hill Road from SH 58 to SH 115 at Meers. Several years ago they paid for the 2” overlay from Porter Hill to SH 58 which covered 7 miles. Once completed, this will put a new surface on the 11 miles from Meers to Porter Hill and is another project that could not have been funded without the good cooperation with Director Tehauno and his staff.

The County road crew recycled the roadway and worked the bar ditches on Woodlawn Road from Crater Road to 115. After we let the traffic on it over the summer, the crew oiled and chipped the road.

The bridge over Boulder Creek on Airport Road, that was started this spring and was scheduled to be completed by the first of July, has been completed. The “road closed” signs have been taken down and traffic is beginning to use the road; however, as of this writing, the striping and putting down grass sod has not been done.

The bridge over Post Oak Creek that replaced the low water crossing on Bishop Road has also been completed. The contractor has to come back and do some final work on drainage problems. The bridge is open to through traffic.

In Cache, the road crew recycled and oiled and chipped 3rd and 4th Streets between C and B Avenues, and Ash and Cherry Avenues between 6th and 5th Streets. The City paid for the materials and the County provided the equipment and labor.

Progress continues on replacing the old truss bridge over West Cache Creek, west of Cache. The basic design has been completed and the engineer had a company collect core samples to determine the depth of the pilings. We have met with the utility companies to find out which ones need to be relocated. A company has been hired to study the environmental impact of the bridge. The construction is scheduled for 2021.

The road crew did some road repair work in Wichita Mtn. Estates and Pecan Valley South. We rented a sweeper attachment for our skid steer to pick up the loose gravel in Pecan Valley South from previous oil and chip projects in that area.

Due to the number of accidents at the intersection at Deyo Mission Road and Lee Blvd, we put up stop signs with red flashing LED lights in hopes that drivers will heed the traffic sign.

We bought the materials for a 30’ x 100’ shed and some of the crew erected it. It will be used to put some of the equipment under so they will be protected when not in use.  

We removed the dirt from the Expo Building at the fair grounds that was used for National Horse play days and the dirt from the Coliseum from the Long Horn Breeder’s Association show. Lately, District 1 puts dirt in and District 3 removes it.

If you have questions or concerns, I can be contacted at This e-mail address is being protected from spambots. You need JavaScript enabled to view it or you may phone the County Barn at 580-429-3217, or the Courthouse office at 580-353-3717.

 

 

PDFPrintE-mail

The Sheriff's House Sale


The Sheriff's House Sale is a public auction to sell repossessed properties, and it occurs periodically throughout the year. Sales are usually held on a scheduled Monday, at 11:00am in the Commissioners' Meeting Room at the Courthouse (Room 302). A list of properties is listed below. Be advised that the list is subject to change, and may not be complete. For a current list, you will have to visit the Sheriff's Office at the Courthouse (Room 102).

 

November 05, 2018

CASE # ADDRESS APPRSL F.D.P. ATTORNEY NEWSPAPER
CJ-2016-798 2204 NW 37th Street 31,000 27-Sep-18 Baer County Times
CJ-2018-130 104 Mohawk Avenue, Geronimo 48,000 27-Sep-18 Kivell County Times
CJ-2018-270 726 NW 31st Street 29,000 27-Sep-18 Kivell County Times
CJ-2017-757 7504 NW Rolando Road 52,000 27-Sep-18 Kivell County Times
CJ-2018-277 411 N. East Drive, Fletcher 39,000 27-Sep-18 Kivell County Times
CJ-2018-364 4910 SE Edinburgh Lane 72,500 04-Oct-18 Shapiro County Times
CJ-2018-261 6415 NW Arrowhead Drive 66,000 04-Oct-18 Hood Constitution
CJ-2016-308 2132 NW Ozmun 35,000 05-Oct-18 Kozeny Constitution
CJ-2018-150 8 NE Cimarron Trail 49,000 04-Oct-18 Kivell County Times
CJ-2018-120 302 Osage Avenue, Geronimo 30,000 04-Oct-18 Kelley Constitution
CJ-2018-83 Read Legal 80,000 04-Oct-18 Mee Constitution
CJ-2018-223 Read Legal 40,000 04-Oct-18 Latham Constitution
CJ-2018-106 3826 NW Arlington 50,000 04-Oct-18 Kozeny Constitution
CJ-2018-73 707 NW Euclid Avenue 29,000 04-Oct-18 Baer County Times
CJ-2018-381 6114 NW Cheyenne Avenue 52,000 04-Oct-18 Baer County Times
CJ-2018-355 Route 1, Box 69, Chattanooga 25,000 04-Oct-18 Baer County Times
CJ-2017-582 8002 NW Baldwin Avenue 82,500 04-Oct-18 Shapiro County Times
CJ-2018-228 406 NW Woodland Drive 32,000 04-Oct-18 Shapiro Constitution
CJ-2018-184 4544 SW Atom Avenue 45,000 04-Oct-18 Shapiro Constitution
CJ-2018-435 1405 NW Hoover 30,000 05-Oct-18 Shapiro Constitution
CJ-2018-180 738 SW 45th Street 19,000 05-Oct-18 Shapiro Constitution
CJ-2018-219 923 SW 34th Street 43,000 04-Oct-18 Kivell County Times
CJ-2018-124 402 NW Rogers Lane, Unit B 30,000 04-Oct-18 Kivell County Times
CJ-2018-240 604 SW 23rd Place 27,500 04-Oct-18 Kivell County Times
CJ-2018-198 1329 NW Cherry Avenue 80,000 04-Oct-18 Kivell County Times
CJ-2018-340 1316 NW Bessie Avenue 80,000 04-Oct-18 Kivell County Times
CJ-2018-208 1720 NW Liberty Avenue 80,000 04-Oct-18 Kivell County Times
CJ-2015-559 104 NW 52nd Street 105,000 04-Oct-18 Shapiro County Times

   